Directional Drilling

 

II. LAYOUT AND DESIGN

A. ACCESS - Heavy equipment is required on both sides of the crossing. To minimize cost, access to either side of the crossing should be provided with the least distance from an improved road. Often the pipeline right-of-way is used for access. All access agreements should be provided by the owner. It is not practical to negotiate such agreements during the bid process.

B. WORK SPACE

1. Rig Side -The rig spread requires a minimum 125-ft. wide by 200-ft. long area. (See Entry LDD-05)This area should extend from the entry point away from the crossing, although the entry point should be at least 10 ft inside the prescribed area. Since many components of the rig spread have no predetermined position, the rig site can be made up of smaller irregular areas. Operations are facilitated if the area is level, hard standing and clear of overhead obstructions. The drilling operation requires large volumes of water for the mixing of the drilling slurry. A nearby source of water is necessary (Figure 2.)

 
 

2. Pipe Side - Strong consideration should be given to provide a sufficient length of work space to fabricate the product pipeline into one string. The width will be as necessary for normal pipeline construction although a work space of 125-ft. wide by 200-ft. long should be provided at the exit point itself. (See Entry LDD-05) The length will assure that during the pullback the pipe can be installed in one uninterrupted operation. Tie-ins of successive strings during the pullback operation increase the risk considerably because the pullback should be continuous (Figure 3).

 
 

C. PROFILE SURVEY - Once the work locations have been chosen, the area should be surveyed and detailed drawings prepared. The eventual accuracy of the drill profile and alignment is dependent on the accuracy of the survey information.


D. PROFILE DESIGN PARAMETERS


1. Depth of Cover
-
Once the crossing profile has been taken and the geotechnical investigation complete, a determination of the depth of cover under the crossing is made. Factors considered may include flow characteristics of the river, the depth of scour from periodic flooding, future channel widening/deepening, and the existence of existing pipeline or cable crossings at the location. It is normally recommended that the minimum depth of cover be 20 ft. under the lowest section of the crossing. While 20 ft. is a recommended depth of cover on a river crossing, crossings of other obstacles may have differing requirements.


2. Penetration Angles and Radius of Curvature -
An entry angle between 8 and 20 can be used for most crossings. It is preferable that straight tangent sections are drilled before the introduction of a long radius curve. The radius of the curve is determined by the bending characteristic of the product pipeline, increasing with the diameter. A general "rule-of-thumb" for the radius of curvature is 100 ft./1-in. diameter for steel line pipe. The curve usually brings the profile to the elevation providing the design cover of the pipeline under the river. Long horizontal runs can be made at this elevation before curving up towards the exit point. Exit angle should be kept between 5 and 12 to facilitate handling of the product pipeline during pullback.


E. DRILL SURVEY - Most down hole survey tools are electronic devices that give a magnetic azimuth (for "right/left" control) and inclination (for "up/down" control). Surface locators can also be used in conjunction with the down hole electronic package.


1. Accuracy -
The accuracy of the drill profile is largely dependent on variations in the earth's magnetic field. For instance, large steel structures (bridges, pilings, other pipelines, etc.) and electric power transmission lines affect magnetic field readings. However, a reasonable drill target at the pilot hole exit location is 10 ft. left or right, and -10 ft. to +30 ft. in length.


2. As-Built Drawings -
Normally, survey calculations are conducted every 30 ft. during pilot hole operations. As-built drawings that are based on these calculations should be provided by the contractor. Alternate methods such as gyroscoping, ground penetrating radar or "intelligent" pigs may also be used to determine the as-built position.