![]() |
Directional Drilling |
| II. LAYOUT AND DESIGN A. ACCESS - Heavy equipment is required on both sides of the crossing. To minimize cost, access to either side of the crossing should be provided with the least distance from an improved road. Often the pipeline right-of-way is used for access. All access agreements should be provided by the owner. It is not practical to negotiate such agreements during the bid process. B. WORK SPACE 1. Rig Side -The rig spread requires a minimum 125-ft. wide by 200-ft. long area. (See Entry LDD-05)This area should extend from the entry point away from the crossing, although the entry point should be at least 10 ft inside the prescribed area. Since many components of the rig spread have no predetermined position, the rig site can be made up of smaller irregular areas. Operations are facilitated if the area is level, hard standing and clear of overhead obstructions. The drilling operation requires large volumes of water for the mixing of the drilling slurry. A nearby source of water is necessary (Figure 2.) |
![]() |
| 2. Pipe Side - Strong consideration should be given to provide a sufficient length of work space to fabricate the product pipeline into one string. The width will be as necessary for normal pipeline construction although a work space of 125-ft. wide by 200-ft. long should be provided at the exit point itself. (See Entry LDD-05) The length will assure that during the pullback the pipe can be installed in one uninterrupted operation. Tie-ins of successive strings during the pullback operation increase the risk considerably because the pullback should be continuous (Figure 3). |
![]() |
| C. PROFILE
SURVEY - Once the work locations
have been chosen, the area should be surveyed and detailed drawings
prepared. The eventual accuracy of the drill profile and alignment is
dependent on the accuracy of the survey information. |